Sneyd Hill Industrial Estate, Stoke

Refurbishment

Units A2, A3 & A4 Sneyd Hill Industrial Estate, Stoke on Trent

  • Refurbishment of 3 adjoining industrial buildings totalling c12,500 Sq Ft
    • Principal Contractor
      • Strip-out previous tenant's fit-out
      • Remove asbestos-cement roof and replace with insulated metal profile roofing system
      • New rooflights
      • Install fall protection system
      • Replace rainwater goods
      • Replace metal cladding system
      • Replace external doors
      • Structural repairs
      • Warehouse floor repairs
      • Break-out external concrete areas
      • External resurfacing
      • Replacement lighting scheme
      • Refurbish WCs
      • New floor coverings
      • Internal & external redecoration

  • Duration: 9 weeks

  • Completed: June 2020

  • Value: c£350k