ERS Medical, Stoke
Refurbishment & Conversion
ERS Medical, Campbell Road, Stoke
- Refurbishment and Conversion of Industrial Unit into Patient Transport Hub
- Principal Contractor; phased works in partially operational premises
- Asbestos Abatement
- Strip-out of previous tenant's fit-out, finishes & chattels
- Layout reconfiguration - internal demolitions and new partition walls
- Form new external openings
- New roller shutters
- External repairs
- Replace rooflights
- Modify, extend and upgrade electrical installation
- Install new ventilation system
- Install new Air-Conditioning
- Service and repair gas-fired heating and hot water system
- New LED lighting scheme
- Addition of electric panel heaters
- Fire-stopping works
- Replace all doorsets and internal joinery
- Install Canteen & Teapoint kitchens
- Replace floor coverings
- New suspended ceilings
- Redecorate throughout
- Duration: 8 weeks
- Value: c£250k
- Completed: August 2021
- Client: ERS Medical