Trinity Court, Wokingham
Refurbishment
Trinity Court, Wokingham
Refurbishment of 13,000ft2 first floor offices
- Principal Contractor
- Remove previous fixtures, fittings & chattels
- Strip-out exisiting partitions, finishes and electrical installation
- Reconfigure layout and install new partitions
- Fire curtains to ceiling voids
- Replace electrical distribution board
- New power and data installations
- Modify raised access flooring
- New LED lighting scheme
- New air-conditioning
- Replace floor finishes
- Replace suspended ceilings
- New internal doors
- Install tea points
- Decorations
- Statutory compliance testing and certification
- Duration: 12 weeks
- Value: c£400k
- Completed: March 2022
- Client: Midos Group