The Mallard Academy, Balby (IN PROGRESS)

Refurbishment

The Mallard Academy, Balby Doncaster

Full, phased internal and external refurbishment of Primary Academy

      • Pitched roof replacement including upgrades to insulation
      • Flat roof replacement
      • Strip out of existing FF&E and finishes
      • Replacement of external doors and windows/curtain wall with modern aluminium
      • Installation of new means of escape doors
      • Firestopping upgrades including replacement of fire doors on compartment lines
      • Replacement of existing and installation of new suspended ceilings
      • Refurbishment of WC’s including new cubicles, vanity units and sanitaryware and wipe-down hygienic finishes
      • Replacement floor finishes
      • Decoration to walls, doors and timber surfaces
      • Upgrades to M&E installations including:
        • Heating & entilation
        • Boiler replacement
        • Replacement hot and cold water distribution
        • Lighting
        • Small power and data
        • Fire alarm, access control and intruder alarm
  • Duration: 38weeks

  • Value: c£3.3m

  • Due for completion: February '26