Refurbishment of the kitchen and South Block at Hall Cross Academy Lower, Doncaster, delivered during the summer holiday period.

Principal Contractor; coordinated asbestos removal, building fabric improvements and kitchen reinstatement within a six-week school holiday programme.

  • Extensive asbestos abatement within the kitchen and South Block
  • Replacement windows and external doors, with associated making good
  • Replacement kitchen roof covering and permanent roof edge protection
  • Temporary removal, protection and reinstatement of commercial kitchen equipment
  • New hygienic wall cladding and suspended ceilings
  • Lighting and emergency lighting upgrades, with associated fire alarm works
  • Fire stopping, pipe lagging and associated mechanical and electrical alterations
  • Reinstatement of finishes, testing, commissioning and deep cleaning

Duration: 6 weeks

Value: c£310k

Completed: August 2026

Client: Exceed Learning Partnership