![](/files/img_cache/795566/995_667_1_1698677105_FirBankCompleted1.jpeg?1698677210)
![](/files/img_cache/795568/995_667_1_1698677105_FirBankCompleted5.jpeg?1698677210)
![](/files/img_cache/795567/995_667_1_1698677105_FirBankCompleted4.jpeg?1698677210)
![](/files/img_cache/795569/995_667_1_1698677105_WhatsAppImage2023-10-27at10.11.28.jpeg?1698677210)
![](/files/img_cache/795570/995_667_1_1698677105_WhatsAppImage2023-10-27at10.11.281.jpeg?1698677211)
![](/files/img_cache/795571/995_667_1_1698677105_WhatsAppImage2023-10-27at10.11.282.jpeg?1698677211)
![](/files/img_cache/795448/995_667_1_1662463166_WhatsAppImage2022-09-05at6.06.58PM1.jpeg?1662463180)
![](/files/img_cache/795449/995_667_1_1662463166_WhatsAppImage2022-09-05at6.06.59PM1.jpeg?1662463180)
![](/files/img_cache/795450/995_667_1_1662463166_WhatsAppImage2022-09-05at6.06.59PM.jpeg?1662463180)
![](/files/img_cache/795451/995_667_1_1662463166_WhatsAppImage2022-09-05at6.06.59PM2.jpeg?1662463180)
![](/files/img_cache/795452/995_667_1_1662463166_WhatsAppImage2022-09-05at6.06.58PM.jpeg?1662463180)
Fir Bank Primary School, Oldham
Refurbishment & Extension
Fir Bank Primary School, Royton, Oldham
Roof and heating replacement and internal remodel of 15,000ft2 existing school plus 1700ft2 Nursery extension. Principal Contractor, Design & Build
- Replacement of flat roof coverings including rainwater goods and rooflights
- Replacement of full heating system
- New boilers
- Distribution pipework
- LST radiators
- BMS
- Pre-fittings for future air-source heat pump
- Overhaul domestic hot water system, including new lagging
- Below-ground drainage repairs and modifications
- New LED lighting scheme, including emergency fittings
- Replacement ceilings throughout
- Refurbishment of 3 classrooms
- Structural modifications
- Patch repairs
- Decorations
- Floor finishes
- Extension
- Temporary access road
- Piling
- Substructure
- Superstructure
- Fit-Out
- Extend heating systems
- Duration: 38 weeks
- Value: c£2.3m
- Completed: August '23
- Client: The Oak Trust