Hall Cross Academy Lower, Doncaster
Kitchen and South Block Refurbishment
Hall Cross Academy Lower, Doncaster
Kitchen and South Block Refurbishment
Refurbishment of the kitchen and South Block at Hall Cross Academy Lower, Doncaster, delivered during the summer holiday period.
Principal Contractor; coordinated asbestos removal, building fabric improvements and kitchen reinstatement within a six-week school holiday programme.
- Extensive asbestos abatement within the kitchen and South Block
- Replacement windows and external doors, with associated making good
- Replacement kitchen roof covering and permanent roof edge protection
- Temporary removal, protection and reinstatement of commercial kitchen equipment
- New hygienic wall cladding and suspended ceilings
- Lighting and emergency lighting upgrades, with associated fire alarm works
- Fire stopping, pipe lagging and associated mechanical and electrical alterations
- Reinstatement of finishes, testing, commissioning and deep cleaning
Duration: 6 weeks
Value: c£310k
Completed: August 2026
Client: Exceed Learning Partnership