Thorp Primary School, Oldham
Roof and Heating Replacement
Thorp Primary School, Oldham
Principal Contractor; Design & Build
- Phased works, minimising impact upon teaching
- Asbestos abatement
- Replace flat roof coverings
- New fascias & rainwater goods
- Underdraw existing canopies
- New courtyard infill roof structure and covering
- Replace heating distribution systems
- Reconfigure domestic hot and cold water systems
- New water heaters
- Replace suspended ceilings
- Internal redecorations
- Replace floor coverings
- Reconfiguration of lighting scheme
- New gym floor
- Duration: 14 weeks
- Value: c£900k
- Completed: October 2021
- Client: The Oak Trust