Units 77-80, The Bridges, Sunderland (IN PROGRESS)

Alterations and Landlords Shell Works

Units 77-80, The Bridges Shopping Centre, Sunderland

Alterations and Landlords Shell Works

      • Asbestos abatement
      • Strip-out & demolitions
      • Structural alterations, including infilling of former staircases and opening up adjoining units to create extended footprint
      • Floor preparation works
      • Internal walls & partitions to form separate tenant/landlords demise areas
      • M&E alterations including Sprinkler Reconfiguration works and installing new incoming electrical supply to new tenant demise
      • Window and door replacement/alteration works
      • Decorations
      • Creation of external loading bay compound
  • Duration: 12 weeks

  • Value: c£900k

  • Due for completion: March '25

  • Client: Evolve Estates